Monday, 8 July 2013

Calamity natural or man-made?




Who is responsible ?


Unprecedented destruction by the rainfall witnessed in Uttarakhand state was attributed, by environmentalists, to unscientific developmental activities undertaken in recent decades and this contributed to high level of loss of property and lives. Roads constructed in haphazard style, new resorts and hotels built on fragile river banks and more than 70 back to back hydro electric projects coming up across the river system of the state lead to a "disaster waiting to happen" as termed by certain environmentalists. As per environmental experts, the tunnels built and blasts undertaken for 70 hydro electric projects contributed to ecological imbalance in the state, with flow of river water restricted and the unscientific real estate activity contributed to higher number of landslides and more flood.







As India picks up the pieces from the worst-ever flash floods in the Himalayas, the nation is beginning to wonder to what extent human intervention – specifically religious tourism and hydroelectric projects –contributed to the disaster. 


The Himalayas are a relatively young mountain range with a fragile geology prone to landslides. The deluge on 17 June destroyed towns, villages, roads and bridges for more than 60 miles along the banks of the Mandakini and the Alaknanda, two important tributaries of the Ganges river. The origin of the disaster is beyond dispute: a glacier ruptured under the pressure of water from a severe cloudburst, raining tonnes of ice, water and rock on the Hindu pilgrimage town of Kedarnath, on the left bank of the Mandakini.









 India boasts of being ranked sixth in terms of largest hydel power generation capacity countries. Domestically, hydel power accounts for 1/4th of India’s dependence on energy. The Hydel Power Report of Uttarakhand published in the year 2008, categorically acclaims that the State has the potential to harness almost 20,000 MW of electricity through hydel power. Blinded with such ambitious target, the State Government failed to notice, either deliberately or otherwise, the very first objective on the same page, which has been reproduced as: “To harness the environment friendly Renewable Energy resources and enhance their contribution to the socioeconomic development of the State.” Another important objective which the State while implementing the said project, was oblivious to, is “To enhance the use of energy sources that assist in mitigating environmental pollution.” 







The current policies, as the CAG Report categorically points out, are aimed at aggravating and not mitigating environmental pollution, and have been a cause of the floods in and around the region. Periphrastically speaking, the ongoing havoc that was witnessed in Uttarakhand was preordained in the report published by the Comptroller and Auditor General of India as late as in 2009, reproaching the Central Government and the Government of Uttarakhand for its dual role of faulty hydro power policy making as well as ineffective policy implementation. 






Some of the main concerns highlighted in the CAG Report are: 

1. Due to the over ambitious policy of the State Government to create multiple river channels, and multiple power projects on the same tributary, a serious endangerment of environment is certainty. With over 42 Projects currently functioning, and 203 projects in construction and clearance stage, at every 6 – 7 kms stretch, there will be a dam to obstruct the flow of the river. 


2. All the projects are based on high seismic areas in and around districts chamoli, rudra prayag, pithoragarh, Almora and despite severe earth quakes in 1720, 1803, 1991, and 1999 the multiplicity of hydro power projects, without adequate counter seismic measures continue to run rogue thereby causing serious risk to the lives of the people. 


3. There is a clear enumeration of Flash Floods which would result in severe destruction to life and property in and around the low lying areas of the hills. Table Appended to the Report has further highlighted various instances wherein such flash floods have occurred previously in the same areas. 


4. No evidence to suggest that for failure to comply with the conditions of Environmental Impact Assessment, a penalty was imposed on the builders.


 5. Failure of the nodal agency to ensure submission of quarterly and half yearly compliance reports by the management. 


6. Flagrant Negligence towards Environmental and Security Concerns. 


7. The adverse impact on the ecology was further underscored by the fact that almost 4 out of 5 Power Projects have shown the complete drying up of river beds to a trickle resulting into severe impairment and devastation of the ecology, and imbalance in the water table resulting into drying up of natural aquifers in the nearby areas. 


8. According to International Standards, the minimum discharge of river downstream should be maintained at 75 % so that the aquatic life remains intact. However, the present projects are discharging downstream river by 90 % and above which results into complete devastation of the aquatic life. 


9. Faulty Pre-Feasibility Survey Reports, which gives inaccurate data for evaluation of the hydro power station, which means serious short comings in ascertaining whether the location to construct is feasible or not, questions on plant efficiency and what would be the impact of soil erosion, etc. remain in a state of serious jeopardy. 


10. As much as 38 % of the total projects which have been granted an Environmental Clearance have failed to carry out mandatory plantation. 




Are we to blame? 


This is one perpetual question, which warrants a sordid introspection. Reports have also suggested that illegal construction of motels, rest houses, guest houses, hotels and restaurants have been made in the river bed, whereas a notification issued by the State Government clearly prohibits any illegal construction in or around 100 metres from the river bed. This is supplementary to the damage that has already been carried out by the Government. Media reports further stipulate that there was no effective functioning authority in the name of “State Disaster Management Authority”. The moot question that now faces us is whether this calamity was “natural” at all, or was it brought about by our own fallacies, inactions, deliberate obliviousness, and negligence. History is replete with instances of civilizations crashing under the might of Natural Forces, and with the present rate of depletion, the future of the Upper Gangetic Basin and the Himalayas hangs in a very delicate balance.